Battery storage returns in Poland
AvenX's October 2026 model estimates a 15.9% project return over 15 years for a typical 100 MW / 400 MWh battery in Poland starting in 2027; this is an illustration, not a forecast.* Polish batteries earn exceptionally well today, but the model expects reserve income to fall steeply as about 5 GW of new batteries compete for a small market.14,27
Key figures
| Poland | |
|---|---|
| Earnings in 2027 (per MW) | €350,000 |
| Earnings over 15 years (per MW) | €2,939,240 |
| Grid fees over 15 years (per MW) | €172,934 |
| Years until the investment is paid back | 6 years |
| Project return (IRR) | 15.9% |
Where do the earnings come from?
A battery earns from trading electricity on wholesale markets, from reserve markets that pay it to stand by and keep the grid stable (FCR and aFRR), and, where one exists, from a capacity market.6 The chart shows the model's earnings per MW of battery power, before costs.
- Wholesale trading
- Reserve markets
- Capacity market
View data as a table
| Year | Wholesale trading | Reserve markets | Capacity market | Total |
|---|---|---|---|---|
| 2027 | €150,000 | €200,000 | €0 | €350,000 |
| 2028 | €154,350 | €100,000 | €0 | €254,350 |
| 2029 | €165,669 | €35,000 | €0 | €200,669 |
| 2030 | €176,474 | €10,000 | €8,547 | €195,021 |
| 2031 | €172,944 | €10,000 | €8,718 | €191,662 |
| 2032 | €169,485 | €10,000 | €8,892 | €188,377 |
| 2033 | €166,095 | €10,000 | €9,070 | €185,165 |
| 2034 | €162,774 | €10,000 | €9,251 | €182,025 |
| 2035 | €159,518 | €10,000 | €9,436 | €178,954 |
| 2036 | €156,328 | €10,000 | €9,625 | €175,953 |
| 2037 | €153,201 | €10,000 | €9,818 | €173,019 |
| 2038 | €150,137 | €10,000 | €10,014 | €170,151 |
| 2039 | €147,134 | €10,000 | €10,214 | €167,348 |
| 2040 | €144,192 | €10,000 | €10,419 | €164,611 |
| 2041 | €141,308 | €10,000 | €10,627 | €161,935 |
What drives the result?
Poland: today's earnings are exceptional, about half of them from the aFRR reserve market,15 but that market buys only 400–500 MW while about 5 GW of batteries are on the way.14,27 The model therefore lowers reserve income steeply by 2030. Grid fees are charged only on energy lost,28 and a small capacity payment starts in 2030.29,13,30
What if the assumptions are wrong?
Earnings are the most uncertain input. The table shows the project return if earnings or the investment differ by 20% from the base case.17,16
| Scenario | Poland |
|---|---|
| Base case | 15.9% |
| Earnings 20% lower | 9.5% |
| Earnings 20% higher | 21.9% |
| Investment 20% higher | 11.5% |
| Investment 20% lower | 22.3% |
View the yearly cash flows (€ thousand per MW)
| Year | Poland |
|---|---|
| 2026 (Investment) | -935 |
| 2027 | 286.3 |
| 2028 | 199.6 |
| 2029 | 150.7 |
| 2030 | 145.1 |
| 2031 | 141.4 |
| 2032 | 137.9 |
| 2033 | 134.3 |
| 2034 | 130.9 |
| 2035 | 127.4 |
| 2036 | 124.1 |
| 2037 | 120.7 |
| 2038 | 117.5 |
| 2039 | 114.2 |
| 2040 | 111.0 |
| 2041 | 107.9 |
Other countries and the full method
Sources
- 6.Enspired. Monthly BESS revenues and market trends, Q2 2026 (opens in a new tab), 2026
- 13.Modo Energy. Poland's BESS investment case is shifting from capacity-backed to merchant-led (opens in a new tab), 20 Mar 2026
- 14.Modo Energy. aFRR in Poland: how Poland's automatic frequency reserve market works (opens in a new tab), 24 Jul 2026
- 15.Modo Energy. Polish BESS revenues rose to 1.89m PLN/MW/yr in August 2026 (opens in a new tab), 4 Sept 2026
- 16.Modo Energy. 2026 Capex Survey (opens in a new tab), 9 Sept 2026
- 17.BESS-Market. CAPEX Benchmark: What does a BESS project cost in 2026? (opens in a new tab), 25 Aug 2026
- 27.Modo Energy. Poland battery pipeline, buildout queue, capacity market (2026) (opens in a new tab), 4 Apr 2026
- 28.Modo Energy. Poland grid fees for BESS (opens in a new tab), 9 Sept 2026
- 29.ESS News. Poland downgrades BESS availability, plummets total awards in capacity market auction (opens in a new tab), Dec 2025
- 30.30rates.com. EUR to PLN today (opens in a new tab), 13 Oct 2026